Client: Thurston’s Group
Principal Contractor: BVMH Groundworks
Project Value: £85k
Duration: 8 Weeks
BVMH conducted and managed following services…
Modular unit groundworks and external finishes
The proposed works consist of Construction and Installation of translocatable container units to create 5 x temporary residential accommodation with associated storage for Southampton Council.
BVMH Groundworks had been appointed as principal contractor to support delivery of the D&B project. The works included taken on D&B responsibility, providing design for all groundworks to include drainage scheme & external works, securing and setting up site and providing welfare facilities, setting out and reduce level digs, form & pour pad foundations, lay new drainage connecting into existing, street works to run and connect new utilities, externals to include paving, tarmac and landscaping. The project was completed within the contract programme and handed over to the client defect free.